Question 43

- (Topic 3)
You are the project manager for the GGG Project and are about to close the project kick off meeting. All of the project team members and the key stakeholders are in attendance. What final item should you talk about before closing the meeting?

Correct Answer:C

Question 44

- (Topic 3)
Ned is the program manager for his organization and he's considering some new materials for his program. He and his team have never worked with these materials before and he wants to
ask the vendor for some additional information, a demon, and even some samples. What type of a document should Ned send to the vendor?

Correct Answer:A

Question 45

- (Topic 1)
Which of the following statements is most accurate about the critical path?

Correct Answer:B

Question 46

- (Topic 4)
Gary is the program manager for his organization. His current program has 432 stakeholders, some of which are external to his organization. He would like to create a chart that identifies each stakeholder's opinion of the program, influence over program decisions, their requirements and affect on program priorities, and other information. What kind of chart should Gary create in this instance?

Correct Answer:B

Question 47

- (Topic 3)
Which of the following statements are true regarding program scope changes?

Correct Answer:ACD

Question 48

- (Topic 2)
Ned is the program manager for his organization and he's considering some new materials for his program. He and his team have never worked with these materials before and he wants to ask the vendor for some additional information, a demon, and even some samples. What type of a document should Ned send to the vendor?

Correct Answer:A