Question 37

- (Topic 3)
You are a program manager for a large construction program. You need to ensure that the projects in the program are in accordance with the schedule. You are tracking start and finish dates for them. Which of the following processes are you on?

Correct Answer:C

Question 38

- (Topic 1)
You are the program manager for your organization. Your program has recently completed its program scope and you've transferred the benefits to the operations of your organization. Before your program is considered closed you must complete some forms and procedures as required by your organization. The requirements to complete the forms and paperwork are also known as what?

Correct Answer:B

Question 39

- (Topic 4)
Which of the following terms is used for a schedule compression technique where two activities that were previously scheduled to start sequentially start at the same time?

Correct Answer:A

Question 40

- (Topic 3)
You are the program manager for the GHT Program for your company. This program has a budget at completion of $789,000 and is currently 40 percent complete, though it was scheduled to be 50 percent at this time. Your program has spent $325,000 of the budget to date. Based on this information, how many pennies is your program losing per dollar spent on the work?

Correct Answer:B

Question 41

- (Topic 3)
You are the program manager for your organization and are about to execute your procurement management plan. You need to procure materials for your program and you want only the vendor to provide you with a price for the goods you need to procure. What type of a document should you provide to the vendor in this scenario?

Correct Answer:B

Question 42

- (Topic 1)
You are the program manager for your organization. Management would like to consider the present value for your program. If your program is predicted to be worth $450,000 in two years what is the present value of the program if the interest rate is six percent?

Correct Answer:A

START PgMP EXAM