Question 31

- (Topic 1)
You are program manager for the HYH Program. Your program governance is requiring you to use earned value management to predict how closely your program is tracking to the cost and schedule baselines and to predict overall program performance. Which earned value management formula can you use to predict how much more will need to be invested in the program based on current program performance?

Correct Answer:D

Question 32

- (Topic 2)
Leigh is working with the project stakeholders to define the project scope. The stakeholders are deciding on what type of flooring their new hotel should have in the lobby. They have narrowed their choices to either carpet or tile. The two acceptable choices of carpet or tile during scope definition is an example of what planning approach?

Correct Answer:A

Question 33

- (Topic 1)
Which of the following documents sets the project objectives?

Correct Answer:C

Question 34

- (Topic 2)
All of the following are resources that you will need to monitor and control in a program environment except for which one?

Correct Answer:B

Question 35

- (Topic 3)
Which of the following shows the ratio between a task's budgeted and actual costs?

Correct Answer:D

Question 36

- (Topic 2)
Program management has several themes that the program manager must be aware of. Which one of the following is not a program management theme?

Correct Answer:D

START PgMP EXAM