Question 25

- (Topic 4)
You are the program manager of the BHG Program. One of the projects in your program will be using new materials that are somewhat untested. You are worried that there may be delays and waste because the project team is unaware of how to accurately use these materials. You elect to send the people that will be using the new materials through training on how to complete their project work. You also allow them to purchase some of the materials to experiment on their use before the actual project work is to be done. You want to ensure that mistakes do not enter into the project. What type of action have you provided in this scenario?

Correct Answer:C

Question 26

- (Topic 3)
You are the program manager for your organization and are coaching your project managers on the program's schedule. Alice wants to know what the schedule control process creates. All of the following are outputs of the schedule control process except for which one?

Correct Answer:B

Question 27

- (Topic 2)
You are the program manager for a large program in your matrix organization. You need to define when the resources in your program will be brought into the program and then released from the program so that the project managers, operational managers, and your program team can plan accordingly. What program management plan defines when resources are needed, how the resources will be obtained, and how the resources may be released from the program?

Correct Answer:B

Question 28

- (Topic 1)
You are the project manager for your organization and are working with the project stakeholders and the business analyst to define all of the deliverables the project is to create. The stakeholders would like the option of adding more deliverables later in the project and keeping the requirements somewhat open for changes. You explain to the business analyst that you need a set of requirements that define exactly what needs to be delivered for the project. What document are you trying to create in this early stage of the project?

Correct Answer:B

Question 29

- (Topic 4)
Which of the following is described in the statement given below?
"It serves as the primary input for the Plan Program Stakeholder Management process, as well as for the distribution of program reports and other communication."

Correct Answer:D

Question 30

- (Topic 3)
Who owns the program?

Correct Answer:C