- (Topic 2)
Julie is the program manager of the NHQ Program for her organization and she believes the program is now complete. Julie is closing her program, and she's working with her program sponsor to review the program's deliverables and benefits. Janet, the program sponsor, is very pleased with the program and agrees that the program has met the program scope. What should Julie and the program sponsor do next?
Correct Answer:D
- (Topic 2)
You are the program manager of the NHQ Program. The program has reached its final deliverable and the certificate of completion has been created for the program. What else should you, the program manager, create at this time?
Correct Answer:D
- (Topic 2)
What cost estimating approach uses the work breakdown structure to create a cost estimate?
Correct Answer:B
- (Topic 1)
What document asks the seller to provide your project with a detailed description of a project solution along with a price to complete the project work?
Correct Answer:A
- (Topic 1)
An organization supports both programs and projects for various industries. What is a portfolio?
Correct Answer:C
- (Topic 1)
You are the program manager for your organization that utilizes vendors from several different organizations. A vendor has submitted an invoice for the work they have completed in your program. You have reviewed the work results and agree with the vendor that their contractual obligation is complete. What should you do next in regard to the vendor's invoice?
Correct Answer:A