You are the program manager for your organization and you're coaching Tom, an aspiring program manager, on program management. Tom is curious about controlling communications. Which one of the following is an output of the communications control process?
Correct Answer:D
- (Topic 2)
You are the program manager for your organization and are working with your program team to create the program scope. Based on the program requirements you have identified the major deliverables of each phase in your program scope. Management has requested that you plan for cost estimating to happen at each phase of the program before continuing the work. Management may elect to cancel the program at the end of each phase based on past performance of the program. What are the reviews of management called at each phase?
Correct Answer:D
- (Topic 2)
You are the program manager for your organization. A new program is about to initiated and Marcy, your assistant, asks you about the themes that all new programs must map to. All of the following are themes that you can discuss with Marcy except for which one is not a program theme?
Correct Answer:B
- (Topic 1)
You are the program manager for your organization. You have created a program that will create things for the organization throughout the program not only at program closure. All of the following are elements that you may transfer to the organization throughout the program's life cycle except for which one?
Correct Answer:C
- (Topic 1)
In which of the following processes is the program charter created?
Correct Answer:C
- (Topic 2)
You are the program manager for the HQM Program. Your program has sixteen constituent projects around the world. You are requiring that each project manager and project management team use the same forms, software, and templates to create standardization in each project. What term is assigned to the forms, templates, and software that your program will provide for your projects?
Correct Answer:D