Question 13

As part of the strategic alignment, you Evaluate organizational strategic goals and objectives using document reviews, interviewing, and other information gathering techniques in order to

Correct Answer:A

Question 14

In your web app company, the portfolio is constantly changing. It is not unusual for a new proposal to be submitted each day and for other components to be terminated as a competitor was first to market. The Portfolio Review Board usually meets daily in this fast- paced environment as it:

Correct Answer:D

Question 15

When it comes to managing a portfolio, you have a variety of assets, plans and tools and techniques used. It requires a good experience to handle all of these artifacts. One of your portfolio team members came to you asking about the relation between the portfolio performance management plan, the portfolio management plan and portfolio strategic plan. What should your answer be?

Correct Answer:B

Question 16

You prepared a portfolio risk management plan when you replaced the previous portfolio manager three years ago. However, recent structural and execution risks have affected the portfolio adversely, resulting in lost opportunities and a decrease in overall return on investment. You are updating the risk management plan as now stakeholders can see its value. In doing so, you can use some portfolio process assets such as:

Correct Answer:B

Question 17

The interest, influence, and communication needs of business operational stakeholders who are looking to ensure alignment between portfolio components, while minimizing negative impact and maximizing positive benefits of all portfolio-managed changes to their business operations, relate to which type of stakeholders?

Correct Answer:D

Question 18

Your company is currently on the verge of bankruptcy due to the lack of transparency within the organization; this alerted the CEO to take decisive actions and request that new reporting lines be established in order to be fully transparent. The new reporting lines triggered changes in roles & responsibilities for managing communication and communication policies & constraints. Where are these changes reflected when it relates to your portfolio?

Correct Answer:C