You are the manager for a governmental portfolio aiming to restructure the roads in your
country. Having a large number of stakeholders including the public, you know that you will be managing the communication closely and that the governance board and the stakeholders would want to check on the progress and performance frequently. For this you have developed a robust communication management plan. What is expected to be found in this plan?
Correct Answer:C
Your company has had a portfolio management process in place for five years at the enterprise level, in its business units, and even in its complex programs. This year the company's Center for Excellence received an award for its work in this area from PMIĀ®. As the Portfolio Manager, you have predefined metrics in place, which are critical because:
Correct Answer:D
Working as the portfolio manager for your business unit of a major aerospace organization means you have a variety of programs, projects, and operational activities under way. You have set up a number of reports on the progress of the portfolio for your various stakeholders, but the best approach is to monitor the progress of the portfolio against:
Correct Answer:A
You are managing a portfolio in a functional organization and resources are shared between operations and projects. You are continuously performing capability and capacity analysis in order to optimize the portfolio. Which of the following capability and capacity analysis is used to limit the number AND size of components the organization can execute?
Correct Answer:D
You are currently defining a hierarchical representation of your portfolio and its components and listing the major and milestone components, including dependencies internal and external to the portfolio with business units. For this you know that you will need multiple inputs. Which of the following are considered inputs in your case?
Correct Answer:B
After the second shutdown of the Government, your Agency Administrator realized that some essential programs had to continue even during the shutdown, some existing work along with some programs and projects in the pipeline perhaps were not needed, and resources may require reallocation. This example shows the:
Correct Answer:B