You are managing a large portfolio and know that you will need to constantly show the progress and status of the portfolio in meeting. For this you have developed a robust roadmap using BI tools. When it comes to Portfolio dependencies, which of the following is true regarding the roadmap?
Correct Answer:A
The Portfolio Management Plan is an important document that is referenced throughout the portfolio life cycle. Which of the following is correct regarding the Portfolio Management Plan purpose and focus?
Correct Answer:C
Various people are responsible for communications to different stakeholder groups, both internal and external to the organization. These delegations of authority are:
Correct Answer:D
By setting up portfolio categories and using a pair-wise comparison approach to rank components, as the portfolio manager, you feel that you are finally setting up and getting people to follow standard portfolio practices. Since portfolio management still is relatively new, progress is under way. As some components are added, and others are not continued, you are making sure if a component is terminated that it does not have dependencies with others in the portfolio. You need to then:
Correct Answer:C
Portfolios tend to have over or under allocations if the portfolio management is of low maturity. Which tool will help you analyze the resources over and under allocations?
Correct Answer:B
Your company works closely with the government on the implementation of water pumps for rural areas. You are constantly dealing with new and updated regulations, and periodically adapting the portfolio to the changes. When it comes to regulatory components, how do you include the components in the portfolio?
Correct Answer:A