An organization has decided to adopt Scrum, but management wants to change the terminology to fit with terminology already used. What will likely happen if this is done?
(choose the best answer)
Correct Answer:D
What is the purpose of a Sprint Review? (choose the best answer)
Correct Answer:C
✑ The Sprint Review is an event that occurs at the end of each Sprint, where the Scrum Team and the stakeholders inspect the Increment and adapt the Product Backlog if needed. The Sprint Review is an opportunity for the Product Owner to validate that the Increment meets their expectations and delivers value to the customers and users. The Sprint Review is also an opportunity for the Developers to demonstrate their work and receive feedback from the Product Owner and the stakeholders.
✑ The purpose of a Sprint Review is to inspect the product Increment with the stakeholders and collect feedback on next steps. The Sprint Review is a collaborative and interactive session where the Scrum Team and the stakeholders discuss what was done in the Sprint, what problems were encountered, what was learned, and what can be improved or changed. The Sprint Review also provides input for updating the Product Backlog to maximize value in future Sprints.
✑ The other options are not valid or relevant purposes of a Sprint Review. They are either too vague, unrelated, or incorrect. They are:
References:
✑ Scrum Guide: https://www.scrumguides.org/scrum-guide.html
✑ Sprint Review: https://www.scrum.org/resources/what-is-a-sprint-review