Question 7

What would be the responsibilities of a self-organizing Development Team?

Correct Answer:B

Question 8

Which approach would you recommend to ensure that the Product Backlog items discussed at Sprint Planning are well understood, actionable, and easier to forecast?

Correct Answer:D
Product Backlog refinement is the act of adding detail, estimates, and order to items in the Product Backlog. This is an ongoing process in which the Product Owner and the Development Team collaborate on the details of Product Backlog items. During Product Backlog refinement, items are reviewed and revised. The Scrum Team decides how and when refinement is done. Refinement usually consumes no more than 10% of the capacity of the Development Team. However, Product Backlog items can be updated at any time by the Product Owner or at the Product Owner’s discretion.

Question 9

A Scrum Master is keeping a list of open impediments, but it is growing and he/she has been able to resolve only a small portion of the impediments.
Which would be the LEAST helpful technique in this situation?

Correct Answer:C
Scrum does not have project managers and arranging a triage meeting would not help accelerate the removal of impediments.

Question 10

Steven, a Scrum Master, has been hired by an organization that is new to Scrum. He has been invited to meet the IT and product management team to kick-off the project. During the meeting the Product Owner asks how many Sprints will be needed to address the entire architecture and infrastructure before working on the features for the new product.
What are the two best responses for Steven to explain how such work is handled in Scrum? (Choose two.)

Correct Answer:BD
When working on complex problems in complex environments, it is difficult to fully predict all future needs and the best solutions will emerge as the work is being performed.

Question 11

When does a new Sprint begin?

Correct Answer:B

Question 12

Steven is a Scrum Master that was hired to help an organization, that is new to Scrum, understands and enacts Scrum effectively.
Which three activities would be acceptable? (Choose three.)

Correct Answer:BCE
The Scrum Master serves the organization in several ways, including: Leading and coaching the organization in its Scrum adoption; Planning Scrum implementations within the organization; Helping employees and stakeholders understand and enact Scrum and empirical product development.