Question 55

- (Exam Topic 3)
Which of the following is False?
A Successful project management team should.

Correct Answer:B

Question 56

- (Exam Topic 4)
Scenario
Additional Information Product Description
Prince2-Practitioner dumps exhibit
Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.
The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors) Introduction
* 1. This document defines the approach to be taken to achieve the required quality levels during the project.
* 2. The Project Board will have overall responsibility for the Quality Management Strategy.
* 3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy. Quality management procedure - Quality standards
* 4. The selected service provider will operate to industry standards for providing outsourced services.
* 5. MFH document standards will be used. Records
* 6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.
* 7. Configuration Item Records will be maintained for each product to describe its status, version and variant.
* 8. Approval records for products that require them will be stored in the quality database. Roles and responsibilities
* 9. The DIT will check that the employment contracts for outsourced staff adhere to employment law.
* 10. Team Managers will provide details of quality checks that have been carried out.
* 11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.
* 12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
Although it is not specified in the current corporate branding standards, the MFH corporate logo should be shown on the front page of the service level agreement.

Correct Answer:C

Question 57

- (Exam Topic 12)
STARTING UP A PROJECT
Here are three actions carried out by the project manager during the ‘starting up a project’ process. As part of which activity (A-F) should each action be carried out?
Choose only one activity for each action. Each activity can be used once, more than once, or not at all.
Prince2-Practitioner dumps exhibit
Solution:
Prince2-Practitioner dumps exhibit

Does this meet the goal?

Correct Answer:A

Question 58

- (Exam Topic 4)
Scenario
Extract from the Project Product Description (with errors)
Prince2-Practitioner dumps exhibit
Which 2 statements apply to the Customer's quality expectations section?

Correct Answer:BE

Question 59

- (Exam Topic 5)
Scenario
Product Summary
A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.
Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.
The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.
Product Breakdown Structure (contains errors)
Prince2-Practitioner dumps exhibit
Extract from Stage Plan for stage 3.
(All entries are true statements but may not be shown under the correct heading or in the correct document).
Prince2-Practitioner dumps exhibit
Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.
The Stage Plan for stage 3 has been produced.
The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.
None of the £500 change budget has been used to date and this is available for the stage. Which 2 statements apply to the Planning assumptions section?

Correct Answer:AE

Question 60

- (Exam Topic 10)
Which of the following principles describes this statement?
"xxx defines tolerances for each project objective to establish limits of delegated authority"

Correct Answer:C

START PRINCE2-Practitioner EXAM