Question 49

- (Topic 2)
Which is an objective of the Closing a Project process?

Correct Answer:B

Question 50

- (Topic 2)
What process provides the information required to decide whether to authorize the delivery of a project?

Correct Answer:B

Question 51

- (Topic 1)
How many tasks does the product-based planning technique describe?

Correct Answer:D

Question 52

- (Topic 4)
Which is NOT a purpose of the Initiating a Project process?

Correct Answer:D

Question 53

- (Topic 2)
Identify the missing word(s) in the following sentence. Quality assurance provides assurance to the [?] that the project is being conducted appropriately whilst Project Assurance provides the same assurance to all the project's stakeholders.

Correct Answer:C

Question 54

- (Topic 4)
What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?

Correct Answer:D