Question 37

- (Topic 2)
Which describes a risk effect?

Correct Answer:C

Question 38

- (Topic 1)
Which regular report provides the Project Board with a summary of stage status?

Correct Answer:C

Question 39

- (Topic 2)
Identify the missing word(s) in the following sentence. During a quality review meeting [ ? ] any identified defects.

Correct Answer:C

Question 40

- (Topic 3)
Which is an objective of the Initiating a Project process?

Correct Answer:C

Question 41

- (Topic 4)
Which is a purpose of an End Project Report?

Correct Answer:B

Question 42

- (Topic 2)
Which PRINCE2 principle helps to address a concern that the project team may NOT have worked on a similar project?

Correct Answer:B

START PRINCE2-Foundation EXAM