- (Topic 4)
Identify the missing words in the following sentence. A purpose of the Plans theme is to [ ?] the project's plans
Correct Answer:C
- (Topic 1)
In what process is the authorization to deliver the project's products given?
Correct Answer:D
- (Topic 4)
Which is a FALSE statement about technical stages?
Correct Answer:C
- (Topic 2)
Which activity takes place within the Managing a Stage Boundary process?
Correct Answer:C
Develop the detailed Business Case
Correct Answer:A
- (Topic 2)
Identify the missing words in the following sentence.
A benefit of adopting PRINCE2 is that it can be applied to [ ? ] - and can easily be implemented alongside specialist techniques.
Correct Answer:A