Ensure that work on products allocated to a team is authorized
Solution:
Does this meet the goal?
Correct Answer:A
- (Topic 4)
Which is a true statement about PRINCE2 event-driven controls
Correct Answer:C
- (Topic 1)
Which describes risk impact?
Correct Answer:C
- (Topic 4)
Which is the Issue Register NOT used for?
Correct Answer:C
- (Topic 2)
Which is one of the six aspects of project performance that needs to be managed?
Correct Answer:C
- (Topic 1)
Which should be provided by a project mandate?
Correct Answer:A