Question 61

- (Topic 2)
Which is a purpose of a Lessons Report?

Correct Answer:A

Question 62

- (Topic 2)
Which product documents the information needed to demonstrate continued business justification?

Correct Answer:A

Question 63

- (Topic 4)
From whom does a Team Manager obtain approval for a completed product?

Correct Answer:C

Question 64

- (Topic 1)
Where should an off-specification be recorded?

Correct Answer:B

Question 65

- (Topic 3)
What product records any time tolerances agreed between the Project Manager and Team Manager?

Correct Answer:B

Question 66

- (Topic 1)
Which statement defines a risk?

Correct Answer:C

START PRINCE2-Foundation EXAM