- (Topic 2)
Which is a purpose of a Lessons Report?
Correct Answer:A
- (Topic 2)
Which product documents the information needed to demonstrate continued business justification?
Correct Answer:A
- (Topic 4)
From whom does a Team Manager obtain approval for a completed product?
Correct Answer:C
- (Topic 1)
Where should an off-specification be recorded?
Correct Answer:B
- (Topic 3)
What product records any time tolerances agreed between the Project Manager and Team Manager?
Correct Answer:B
- (Topic 1)
Which statement defines a risk?
Correct Answer:C