- (Topic 4)
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
Correct Answer:B
- (Topic 2)
Which of the following are placed at selected points in the work breakdown structure (WBS) for performance measurement?
Correct Answer:A
- (Topic 5)
An example of a group decision-making technique is:
Correct Answer:A
- (Topic 1)
Which characteristics do effective project managers possess?
Correct Answer:A
- (Topic 4)
The approaches, tools, and data sources that will be used to perform risk management on a project are determined by the:
Correct Answer:A
- (Topic 4)
Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?
Correct Answer:C