Question 115

- (Topic 3)
The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:

Correct Answer:C

Question 116

- (Topic 5)
Lessons learned documentation is gathered during which of the following Project Management Process Groups?

Correct Answer:C

Question 117

- (Topic 3)
A process is defined as:

Correct Answer:A

Question 118

- (Topic 1)
Which of the following methods is a project selection technique?

Correct Answer:C

Question 119

- (Topic 3)
A tool or technique used in the Control Procurements process is:

Correct Answer:B

Question 120

- (Topic 3)
The project manager has requested all expert team members to complete an anonymous questionnaire to identify possible risks. This is an example of a technique known as the:

Correct Answer:C

START PMP EXAM