Question 61

- (Topic 5)
An output of the Direct and Manage Project Work process is:

Correct Answer:A

Question 62

- (Topic 3)
An input to Conduct Procurements is:

Correct Answer:C

Question 63

- (Topic 2)
During what process is the quality policy determined?

Correct Answer:C

Question 64

- (Topic 4)
One of the fundamental tenets of modern quality management states that quality is:

Correct Answer:A

Question 65

- (Topic 3)
Which of the following is a component of three-point estimates?

Correct Answer:B

Question 66

- (Topic 1)
Technical capability, past performance, and intellectual property rights are examples of:

Correct Answer:B