- (Topic 5)
Which of the following is a measure of the value of work completed compared to the actual cost or progress made on the project?
Correct Answer:B
- (Topic 2)
Which type of chart is a graphic representation of a process showing the relationships among process steps?
Correct Answer:C
- (Topic 2)
Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?
Correct Answer:C
- (Topic 1)
Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:
Correct Answer:A
- (Topic 4)
Using the following data, what is the Schedule Performance Index (SPI)? EV= $500 PV= $750 AC= $1000 BAC= $1200
Correct Answer:A
- (Topic 3)
Based on the following metrics: EV=$20,000, AC=$22,000, and PV=$28,000, what is the project CV?
Correct Answer:B