Question 67

Billy is the project manager of the HAR Project and is in month six of the project. The project is scheduled to last for 18 months. Management asks Billy how often the project team is participating in risk reassessment in this project. What should Billy tell management if he's following the best practices for risk management?

Correct Answer:C

Question 68

You and your project team are just starting the risk identification activities for a project that is scheduled to last for 18 months. Your project team has already identified a long list of risks that need to be analyzed. How often should you and the project team do risk identification?

Correct Answer:C

Question 69

Elizabeth is a project manager for her organization and she finds risk management to be very difficult for her to manage. She asks you, a lead project manager, at what stage in the project will risk management become easier. What answer best resolves the difficulty of risk management practices and the effort required?

Correct Answer:A

Question 70

You work as a project manager for SoftTech Inc. You have implemented the risk action plan and it was not effective. What type of plan should you as a project manager will create for implementation if a selected risk strategy fails to be fully effective?

Correct Answer:C

Question 71

What approach can a project manager use to improve the project's performance during qualitative risk analysis?

Correct Answer:C

Question 72

You work as a project manager for BlueWell Inc. You are preparing to plan risk responses for your project with your team. How many risk response types are available for a negative risk event in the project?

Correct Answer:A