Question 49

When faced with a tight timeline, the project sponsor suggests that the project team start development without creating traceability artifacts What should the business analyst do?

Correct Answer:B

Question 50

The business analyst generated a design specification for a new product. What is the best type of formal review to conduct with the customer to establish an approved requirements baseline?

Correct Answer:B

Question 51

A business analyst has been assigned to a project team that is redesigning the company's website The business analyst has been documenting the relationships between requirements and has found requirements that do not trace to a business need.
Which type of requirements are these?

Correct Answer:A

Question 52

How can a SWOT analysis help when deciding between several possible options to address a business problem?

Correct Answer:A

Question 53

Company A would like to enter into a new market. The business analyst has been assigned lo a project for which nobody in Company A has any prior experience. The project manager has asked the business analyst to assist in resource planning.
What should the business analyst recommend to the project manager?

Correct Answer:C

Question 54

Two weeks prior to the delivery date, a customer changes the business requirements. What should the business analyst do?

Correct Answer:C

START PMI-PBA EXAM