Question 37

The business analyst receives multiple changes from different stakeholders during the requirements gathering phase of a project. How should the business analyst track the requirements throughout the lifecycle of the project to secure the delivery of the expected solution?

Correct Answer:A

Question 38

A project team has 120 days to deliver a solution, but the stakeholders have too many requirements for the delivery window. What requirements prioritization technique should be used to determine which
requirements will be delivered?

Correct Answer:D

Question 39

The software developers have delivered a completed solution. The quality assurance team has passed the solution. What should the business analyst do next?

Correct Answer:A

Question 40

A business analyst is working with the project manager, company auditors, and project stakeholders to determine whether formal signoff should be required for the project. For which reason would the business analyst recommend formal signoff to the group?

Correct Answer:C

Question 41

A system enhancement project has been initiated to address the concerns of an external group of stakeholders not included in the first release. What should be done to ensure stakeholder satisfaction with
the enhancement?

Correct Answer:A

Question 42

A stakeholder has rejected a project's deliverable because it does not meet the original business need. It is further determined that the deliverable does not meet the requirements identified in the baseline.
What is the best approach to resolve this issue?

Correct Answer:A

START PMI-PBA EXAM