- (Topic 4)
Which of the following is a set of interrelated actions and activities performed to achieve a prespecified product, result, or service?
Correct Answer:B
- (Topic 3)
A project management office manages a number of aspects including the:
Correct Answer:D
- (Topic 1)
An input to the Plan Cost Management process is:
Correct Answer:C
- (Topic 3)
What are the formal and informal policies, procedures, and guidelines that could impact how the project's scope is managed?
Correct Answer:A
- (Topic 1)
Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?
Correct Answer:D
- (Topic 3)
A collection of projects managed as a group to achieve strategic objectives is referred to as a:
Correct Answer:D