- (Topic 3)
Which Develop Schedule tool and technique produces a theoretical early start date and late start date?
Correct Answer:A
- (Topic 5)
An input to the Collect Requirements process is the:
Correct Answer:A
- (Topic 5)
Which of the following response strategies are appropriate for negative risks or threats?
Correct Answer:D
- (Topic 4)
What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000
Correct Answer:D
- (Topic 1)
An output of the Plan Quality Management process is:
Correct Answer:A
- (Topic 3)
During which process group is the quality policy determined?
Correct Answer:C