Question 91

- (Topic 5)
The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:

Correct Answer:B

Question 92

- (Topic 4)
Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?

Correct Answer:C

Question 93

- (Topic 2)
The following chart contains information about the tasks in a project.
PMI-100 dumps exhibit
Based on the chart, what is the cost variance (CV) for Task 6?

Correct Answer:D

Question 94

- (Topic 1)
External organizations that have a special relationship with the enterprise and provide specialized expertise are called:

Correct Answer:B

Question 95

- (Topic 4)
Which Perform Quality Control tool graphically represents how various elements of a system interrelate?

Correct Answer:B

Question 96

- (Topic 2)
Processes in the Initiating Process Group may be completed at the organizational level and be outside of the project's:

Correct Answer:A