Question 85

- (Topic 2)
The following is a network diagram for a project.
PMI-100 dumps exhibit
The total float for the project is how many days?

Correct Answer:B

Question 86

- (Topic 2)
A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?

Correct Answer:A

Question 87

- (Topic 1)
Which tool or technique is used to manage change requests and the resulting decisions?

Correct Answer:A

Question 88

- (Topic 1)
An input to the Plan Stakeholder Management process is:

Correct Answer:D

Question 89

- (Topic 1)
An input to the Manage Project Team process is:

Correct Answer:A

Question 90

- (Topic 5)
A project lifecycle is defined as:

Correct Answer:A

START PMI-100 EXAM