Question 79

- (Topic 2)
The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:

Correct Answer:C

Question 80

- (Topic 1)
Which Collect Requirements output links the product requirements to the deliverables that satisfy them?

Correct Answer:B

Question 81

- (Topic 3)
An output of the Develop Project Team process is:

Correct Answer:B

Question 82

- (Topic 2)
Which project risk listed in the table below is most likely to occur?
PMI-100 dumps exhibit

Correct Answer:B

Question 83

- (Topic 3)
An input of the Control Schedule process is the:

Correct Answer:D

Question 84

- (Topic 1)
What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

Correct Answer:C

START PMI-100 EXAM