Question 73

- (Topic 2)
A risk that arises as a direct result of implementing a risk response is called a:

Correct Answer:D

Question 74

- (Topic 5)
Which process requires implementation of approved changes?

Correct Answer:A

Question 75

- (Topic 3)
Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?

Correct Answer:A

Question 76

- (Topic 3)
Work performance information and cost forecasts are outputs of which Project Cost Management process?

Correct Answer:D

Question 77

- (Topic 2)
Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?

Correct Answer:D

Question 78

- (Topic 3)
What name(s) is (are) associated with the Plan-Do-Check-Act cycle?

Correct Answer:C