Question 67

- (Topic 4)
Which tool or technique is used in Manage Stakeholder Expectations?

Correct Answer:B

Question 68

- (Topic 4)
The project scope statement and resource calendars are inputs to which Project Time Management process?

Correct Answer:C

Question 69

- (Topic 5)
Which statement correctly describes the value of a business case?

Correct Answer:A

Question 70

- (Topic 2)
Which tool or technique is required in order to determine the project budget?

Correct Answer:B

Question 71

- (Topic 2)
Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?

Correct Answer:A

Question 72

- (Topic 5)
Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?

Correct Answer:A