- (Topic 4)
Which tool or technique is used in Manage Stakeholder Expectations?
Correct Answer:B
- (Topic 4)
The project scope statement and resource calendars are inputs to which Project Time Management process?
Correct Answer:C
- (Topic 5)
Which statement correctly describes the value of a business case?
Correct Answer:A
- (Topic 2)
Which tool or technique is required in order to determine the project budget?
Correct Answer:B
- (Topic 2)
Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?
Correct Answer:A
- (Topic 5)
Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?
Correct Answer:A