- (Topic 1)
Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?
Correct Answer:D
- (Topic 4)
As the project progresses, which of the following is routinely collected from the project activities?
Correct Answer:D
- (Topic 1)
Which item is an input to the Define Activities process?
Correct Answer:D
- (Topic 4)
The PV is $1000, EV is $2000, and AC is $1500. What is CPI?
Correct Answer:A
- (Topic 5)
Activity cost estimates are quantitative assessments of the probable costs required to:
Correct Answer:B
- (Topic 4)
Which of the following factors is lowest at the start of the project?
Correct Answer:A