Question 61

- (Topic 1)
Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?

Correct Answer:D

Question 62

- (Topic 4)
As the project progresses, which of the following is routinely collected from the project activities?

Correct Answer:D

Question 63

- (Topic 1)
Which item is an input to the Define Activities process?

Correct Answer:D

Question 64

- (Topic 4)
The PV is $1000, EV is $2000, and AC is $1500. What is CPI?

Correct Answer:A

Question 65

- (Topic 5)
Activity cost estimates are quantitative assessments of the probable costs required to:

Correct Answer:B

Question 66

- (Topic 4)
Which of the following factors is lowest at the start of the project?

Correct Answer:A