Question 127

Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?

Correct Answer:C

Question 128

Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?

Correct Answer:D

Question 129

Which of the following Project Communication Management processes uses performance reports as an input?

Correct Answer:C

Question 130

Which characteristic do projects and operational work share in common?

Correct Answer:B

Question 131

Projects can be divided into phases to provide better management control. Collectively, what are these phases known as?

Correct Answer:C

Question 132

Organizations perceive risks as:

Correct Answer:B

START PMI-001 EXAM