Question 109

Which input will be used when tasked with developing the human resource plan?

Correct Answer:B

Question 110

In the basic communication model, which term refers to the method that is used to convey the message?

Correct Answer:C

Question 111

During which process does the project team receive bids and proposals?

Correct Answer:A

Question 112

Which tools or techniques are used in the Plan Schedule Management process?

Correct Answer:D

Question 113

Who MUST know when a risk event occurs so that a response can be implemented?

Correct Answer:C

Question 114

Change requests are an output from which Project Integration Management process?

Correct Answer:A