Question 85

Which type of chart is a graphic representation of a process showing the relationships among process steps?

Correct Answer:C

Question 86

A given schedule activity is most likely to last four weeks. In a best-case scenario, the
schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?

Correct Answer:C

Question 87

Technical capability, past performance, and intellectual property rights are examples of:

Correct Answer:B

Question 88

A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable. This could have been avoided if the project team had implemented:

Correct Answer:D

Question 89

Outputs of the Control Communications process include:

Correct Answer:B

Question 90

What risk technique is used to quantify the probability and impact of risks on project objectives?

Correct Answer:D