Which type of chart is a graphic representation of a process showing the relationships among process steps?
Correct Answer:C
A given schedule activity is most likely to last four weeks. In a best-case scenario, the
schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?
Correct Answer:C
Technical capability, past performance, and intellectual property rights are examples of:
Correct Answer:B
A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable. This could have been avoided if the project team had implemented:
Correct Answer:D
Outputs of the Control Communications process include:
Correct Answer:B
What risk technique is used to quantify the probability and impact of risks on project objectives?
Correct Answer:D