A project is executed to migrate all data to a single system following the merger of two companies. The team validates that system performance will not be impacted. Which of the following did the team perform?
Correct Answer:C
Stress testing is a type of performance testing that evaluates how a system behaves under extreme load conditions, such as high volume of data, concurrent users, or transactions12. Stress testing can help to identify the system’s breaking point, bottlenecks, and resource limitations, and to ensure that the system can recover from failures and maintain its functionality34. In this case, the team performed stress testing to validate that system performance will not be impacted by migrating all data to a single system following the merger of two companies. This implies that the team simulated a high amount of data transfer and processing, and measured the system’s response time, throughput, availability, and reliability under such load. Stress testing is better than the other options because:
✑ Regression testing is a type of functional testing that verifies that a system’s existing features and functionality are not affected by a change or an update56. Regression testing does not focus on system performance or load conditions, but rather on system correctness and quality.
✑ Smoke testing is a type of functional testing that checks the basic functionality and stability of a system before performing more detailed and comprehensive testing78. Smoke testing does not measure system performance or load conditions, but rather ensures that the system is ready for further testing.
✑ Automation testing is a technique of using software tools or scripts to execute test cases and compare the actual results with the expected results910. Automation testing is not a specific type of testing, but rather a way of performing testing. Automation testing can be applied to various types of testing, including stress testing, regression testing, and smoke testing.
References = CompTIA Project+ Certification Study Guide, CompTIA Project+ Certification Exam Objectives, What is Stress Testing?1, Stress Testing: A Complete Guide2, What is Regression Testing?3, Regression Testing: A Complete Guide4, What is Smoke Testing?5, Smoke Testing: A Complete Guide6, What is Automation Testing?7, Automation Testing: A Complete Guide8
Which of the following would be MOST beneficial to do before a call to ensure all meeting items are addressed and the correct participants attend?
Correct Answer:B
The project manager should distribute an agenda before a call to ensure all meeting items are addressed and the correct participants attend. An agenda is a document that outlines the purpose, topics, and objectives of a meeting. It also includes information such as date, time, duration, location, attendees, and roles. Distributing an agenda can help to prepare the participants for the meeting, set clear expectations, and facilitate a productive and focused discussion12
A stakeholder raises a concern with a project manager because of the number of emails that have been received before a coding release. Which of the following actions should the project manager take next?
Correct Answer:D
When stakeholders express concerns about the volume of communication, it’s important to review and adjust the communication plan to ensure it meets the project’s needs and stakeholders’ preferences. A RACI matrix is useful for defining roles and responsibilities but does not address communication frequency or methods directly. Escalating the issue may not be necessary if it can be resolved by revising the plan. Informing the CCB (Change Control Board) to stop communication is not advisable as the CCB’s role is to oversee changes, not to manage day-to-day communications. References
= The CompTIA Project+ Certification Study Guide provides detailed information on managing the project life cycle, establishing communication plans, and handling stakeholder concerns1.
A project manager and team are reviewing a task that is supposed to take nine days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional five days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?
Correct Answer:B
The total amount that should be budgeted for the task is calculated by adding the expected value of the risk to the original estimate. The expected value of the risk is the product of the probability and the impact of the risk. In this case, the expected value of the risk is 0.2 x (5 days and $1,000) = 1 day and $200. Therefore, the total amount that should be budgeted for the task is 9 days and $3,000 + 1 day and $200 = 10 days and $3,2001.
Which of the following is a reason to use a SOW on a project?
Correct Answer:C
A statement of work (SOW) is a formal document that defines the entire scope of work involved for a vendor and clarifies deliverables, costs, and timeline1. It serves as a contractual agreement between a vendor and a client, providing a comprehensive description of the work to be performed2. A reason to use a SOW on a project is to ensure the team stays within the scope of the contract, as it outlines what the team will and won’t do on a project, saving from painful client negotiations and protecting
the timeline and the bottom line3. References = CompTIA Project+ PK0-005 Certification Study Guide, Chapter 3: Initiating Projects Part 1, page 63; What Is a Statement of Work? Definition & Examples, Introduction and What Is a Statement of Work (SOW) In Project Management? sections; Statement Of Work Ultimate Guide: Simple Definition & Template, Introduction and What is a Statement of Work? sections; What Is a Statement of Work (SOW)? - Coursera, Introduction section.
After a release, the project sponsor received an escalation from an executive about the
extension of the downtime after the scheduled window. Which of the following should be added to the issue log?
Correct Answer:C
Customer notification should be added to the issue log after receiving an escalation from an executive about the extension of the downtime after the scheduled window. Customer notification is a communication activity that informs the customers about any issues or changes that may affect their satisfaction or expectations. Customer notification can help to maintain trust, transparency, and goodwill with the customers and prevent any negative impacts on their business operations or experience.