A meeting agenda included the following items:
. Review the goals of the project.
. Review the progress of the project.
. Discuss if the project is ready to move forward.
Which of the following best describes this type of meeting?
Correct Answer:D
A gate review is a type of meeting that evaluates the completion and quality of a project stage and decides whether the project can proceed to the next stage. A gate review is a formal governance step that involves reviewing the goals, progress, risks, deliverables, and benefits of the project, and discussing if the project is still aligned with the business strategy and stakeholder expectations. A gate review can have different outcomes, such as go, kill, hold, recycle, or conditional go, depending on the assessment of the project status and viability123. References = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 9: Project Change Management, p. 323; Everything Project Managers Need To Know About Gate Reviews | monday.com Blog; Gate reviews: What to do and why you need them - Rebel’s Guide to Project Management; Gates and How to Operate Them - GenSight
A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?
Correct Answer:A
The project manager should validate against the scope statement and ask for sign-off after a system was implemented and testing was successfully completed. The scope statement is a document that defines and documents the project scope, objectives, deliverables, requirements, assumptions, and constraints. The scope statement can help to establish a common understanding and agreement between the project manager and the stakeholders on what the project aims to achieve and deliver. Validating against the scope statement means checking whether the project deliverables meet the agreed-upon scope criteria and quality standards. Asking for sign-off means requesting formal acceptance and approval of the project deliverables from the stakeholders.
A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date. Which of the following should the project manager do first?
Correct Answer:B
The project manager should review the requested change first to assess its impact, feasibility, and alignment with the project objectives and scope. Reviewing the change will help the project manager to determine if the change is necessary, beneficial, and acceptable to the stakeholders. The project manager should also consider the risks, costs, and quality implications of the change before proceeding to the next steps of the change management process123. References = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 9: Project Change Management, p. 323; 5 Steps in the Change Management Process | HBS Online; 8 Steps for an Effective Change Management Process - Smartsheet
Which of the following activities are performed during the closing phase? (Select three).
Correct Answer:BDF
The closing phase of a project involves finalizing all project activities, delivering the project deliverables, releasing the project resources, and closing out the project accounts. Some of the activities that are performed during this phase are12:
•Recognizing project team efforts and rewarding team members. This is an important activity to acknowledge the contributions of the project team, celebrate the project success, and motivate the team members for future projects. Recognition and rewards can be given in various forms, such as certificates, bonuses, gifts, or feedback.
•Revoking resource credentials from the system. This is a security measure to ensure that the project resources, such as staff, contractors, vendors, or consultants, do not have access to the project systems, data, or assets after the project is completed. Revoking credentials can prevent unauthorized access, data breaches, or misuse of project resources.
•Informing the functional manager about the release of resources. This is a communication activity to notify the functional manager, who is responsible for the allocation and management of resources, that the project resources are no longer needed and can be reassigned to other projects or tasks. Informing the functional manager can help to optimize the resource utilization, avoid resource conflicts, and plan for future resource needs.
References = CompTIA Project+ PK0-005 Certification
Which of the following statements best describes a content management system?
Correct Answer:C
A content management system (CMS) is a software application that allows users to create, manage, and deliver content via digital channels, such as websites, blogs, or social media12. A CMS enables multiple contributors to access, edit, and publish content without requiring technical knowledge or coding skills34. A CMS also provides features such as templates, workflows, media libraries, and analytics to help users design, organize, and optimize their content56. References = CompTIA Project+ Certification Study Guide7, CompTIA Project+ Certification Exam Objectives8, What Is a Content Management System (CMS)?1, What is a Content Management System (CMS) | Oracle2, What is a Content Management System (CMS)? | Adobe Basics3, What is a CMS?4, What is a Content Management System?5, Content Management System (CMS) - Definition from Techopedia6
Which of the following is a capital expense?
Correct Answer:B
A capital expense is the cost of acquiring or making improvements to fixed assets that have a useful life of more than one year1. A building purchase is an example of a capital expense, as it is a long-term investment that increases the value of the company’s assets2. Building lease, maintenance, and insurance are not capital expenses, as they are recurring or short-term costs that do not increase the value of the company’s assets3.