Question 13

Which of the following would indicate a project manager is working in a matrix-based organization?

Correct Answer:A

Question 14

A project manager procures additional resources from a local company. Which of the following-describes this event?

Correct Answer:A

Question 15

During a project assessment, a project manager determines the initial project cost estimates were incorrect, and there is not enough budget left, including reserves, to complete the project.
Which of the following actions should the project manager take?

Correct Answer:A
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 233

Question 16

A team member was replaced on a project by a new team member of equal capability. Which of the following should the project manager do FIRST?

Correct Answer:D

Question 17

The design activity of a project has the following cost attributes: PV = 100,000
EV = 20,000
AC = 90,000
Based on this scenario, calculate the schedule variance.

Correct Answer:A

Question 18

A project manager is assigned to an ongoing project. Which of the following is the FIRST document the protect manager should review?

Correct Answer:A