Question 7

A project manager receives a call from the area regional building department and is informed that, upon inspection, waterlines from public water access to the project building do not meet local material and installation code specifications. Which of the following items BEST describes the unmet objective?

Correct Answer:D

Question 8

A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date and quality of the deliverable cannot change. Which of the following activities should the project manager perform NEXT?

Correct Answer:A

Question 9

Which of the following activity sequencing techniques uses nodes to symbolize activities and arrows to show how their dependencies are connected?

Correct Answer:D

Question 10

One deliverable failed during testing, and this has already happened several times.
Which of the following tools is MOST appropriate for the project team to use to determine the cause of the problem?

Correct Answer:B
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 322

Question 11

A project team is spread between two countries on different continents. Which of the following factors are MOST likely to influence communication methods selected for the communication plan? (Select TWO).

Correct Answer:CD

Question 12

An organization has determined that all projects must use a remote dashboard to allow portfolio management. Which of the following would enforce this directive?

Correct Answer:A