- (Topic 10)
Which process analyses services that are no longer viable and when they should be retired?
Correct Answer:B
- (Topic 10)
Which function is responsible for the closure of an incident record?
Correct Answer:B
- (Topic 3)
A Service design package (SDP) would normally be produced for which of the following?
1. A new IT service
2. A major change to an IT service
3. An emergency change to an IT service
4. An IT service retirement
Correct Answer:B
- (Topic 10)
. Which is an outcome of service design?
Correct Answer:B
- (Topic 1)
What would you call the groups of people who have an interest in the activities, targets, resources and deliverables from service management?
Correct Answer:B
- (Topic 6)
Which process is responsible for recording the current details, status, interfaces and dependencies of all services that are being run or being prepared to run in the live environment?
Correct Answer:B