Question 43

In which of the following test documents would you expect to find test exit criteria described9

Correct Answer:D
Test exit criteria are the conditions that must be fulfilled before concluding a particular testing phase. These criteria act as a checkpoint to assess whether we have achieved the testing objectives and are done with testing1. Test exit criteria are typically defined in the test plan document, which is one of the outputs of the test planning phase. The test plan document describes the scope, approach, resources, and schedule of the testing activities. It also identifies the test items, the features to be tested, the testing tasks, the risks, and the test deliverables2. According to the ISTQB® Certified Tester Foundation Level Syllabus v4.0, the test plan document should include the following information related to the test exit criteria3:
✑ The criteria for evaluating test completion, such as the percentage of test cases
executed, the percentage of test coverage achieved, the number and severity of defects found and fixed, the quality and reliability of the software product, and the stakeholder satisfaction.
✑ The criteria for evaluating test process improvement, such as the adherence to the
test strategy, the efficiency and effectiveness of the testing activities, the lessons learned and best practices identified, and the recommendations for future improvements.
Therefore, the test plan document is the most appropriate test document to find the test exit criteria described. The other options, such as test design specification, project plan, and requirements specification, are not directly related to the test exit criteria. The test design specification describes the test cases and test procedures for a specific test level or test type3. The project plan describes the overall objectives, scope, assumptions, risks, and deliverables of the software project4. The requirements specification describes the functional and non-functional requirements of the software product5. None of these documents specify the conditions for ending the testing process or evaluating the testing
outcomes. References = ISTQB® Certified Tester Foundation Level Syllabus v4.0, Entry and Exit Criteria in Software Testing | Baeldung on Computer Science, Entry And Exit Criteria In Software Testing - Rishabh Software, Entry and Exit Criteria in Software Testing Life Cycle - STLC [2022 Updated] - Testsigma Blog, ISTQB® releases Certified Tester Foundation Level v4.0 (CTFL).

Question 44

Which of the following lists factors That contribute to PROJECT risks?

Correct Answer:A
Project risks are the uncertainties or threats that may affect the project objectives, such as scope, schedule, cost, and quality. According to the ISTQB Certified Tester Foundation Level (CTFL) v4.0 syllabus, some of the factors that contribute to project risks are:
✑ Skill and staff shortages: This factor refers to the lack of adequate or qualified human resources to perform the project tasks. This may result in delays, errors, rework, or low productivity.
✑ Problems in defining the right requirements: This factor refers to the difficulties or ambiguities in eliciting, analyzing, specifying, validating, or managing the requirements of the project. This may result in misalignment, inconsistencies, gaps, or changes in the requirements, affecting the project scope and quality.
✑ Contractual issues: This factor refers to the challenges or disputes that may arise from the contractual agreements between the project parties, such as clients, suppliers, vendors, or subcontractors. This may result in legal, financial, or ethical risks, affecting the project delivery and satisfaction.
The other options are not correct because they list factors that contribute to PRODUCT risks, not project risks. Product risks are the uncertainties or threats that may affect the quality or functionality of the software product or system. Some of the factors that contribute to product risks are:
✑ Poor software quality characteristics: This factor refers to the lack of adherence or
compliance to the quality attributes or criteria of the software product or system, such as reliability, usability, security, performance, or maintainability. This may result in defects, failures, or dissatisfaction of the users or stakeholders.
✑ Software does not perform its intended functions: This factor refers to the deviation
or discrepancy between the expected and actual behavior or output of the software product or system. This may result in errors, faults, or malfunctions of the software product or system.
References = ISTQB Certified Tester Foundation Level (CTFL) v4.0 syllabus, Chapter 1: Fundamentals of Testing, Section 1.5: Risks and Testing, Pages 14-16.

Question 45

You are testing an e-commerce system that sporadically fails to properly manage customers' shopping carts. You have stressed the urgency of this situation to the development manager and development team and they recognize the priority of resolving the underlying defect. The development team is waiting for more information, which you will include in your defect report. Given the following items of information they are included in a typical defect report:
* 1. The expected results
* 2. The actual results
* 3. The urgency and priority to fix this
* 4. The date and author of the defect report
* 5. A description of the defect in order to reproduce, including screenshots and database dumps
Which of these items will be MOST useful to the developers to help them identify and remove the defect causing this failure?

Correct Answer:A
When developers are trying to identify and remove a defect, they need clear information on what went wrong and what was expected. The items that will be most useful to developers in this context are the expected results (item 1), the actual results (item 2), and a description of the defect including steps to reproduce, screenshots, and database dumps (item 5). This information helps developers understand the nature of the defect and provides the necessary details to reproduce and diagnose the issue effectively. References:
✑ ISTQB Certified Tester Foundation Level Syllabus v4.0, Section 5.5.1.