Northern Trail Outfitters (NTO) wants to track and report on individual tasks completed, including parts consumed and pricing details, as part of the Work Order completion process. NTO wants to schedule one or multiple tasks to different Technicians as needed.
How should the Consultant meet the requirement utilizing the standard Salesforce Field Service Data Model?
Correct Answer:D
Service resources at universal container UC frequently work in more than one service territory the current scheduling policy looks only at primary territory while us still want to optimizer to use the service resource primary when scheduling, UC also wants the scheduling policy to look at the resources secondary services territory Which two scheduling policy changes should a consultant recommend?
Choose 2 answers
Correct Answer:BC
A technician reported that the travel time calculated between appointments is often two short because job delays throughout the day.
Which setting should a consultant consider to improve travel time accuracy?
Correct Answer:D
Universal Containers (UC) has 140 service resources who handle 2,400 service appointments per day.
How should UC define Service Territories to ensure a high quality of optimization and dispatcher experience?
Correct Answer:A
Universal containers want technicians to view work progress through the work order line-item card in the field service lightning mobile app.
Which configuration steps should a consultant take to meet this requirement?
Correct Answer:A
To ensure that preventative maintenance work can be completed on time. Universal Containers wants to automatically generate Work Orders 14 days before the next suggested maintenance date.
How should the Consultant meet this requirement?
Correct Answer:A