Question 7

Universal Containers performs multi-staged jobs, where the second job can only begin after completion of the first job. How should a Consultant recommend implementing this process?

Correct Answer:A

Question 8

Which two configurations can companies add to brand the Field Service mobile app?

Correct Answer:B

Question 9

Universal Containers wants to encourage their Technicians to identify sales opportunities in the field. Which option should a Consultant recommend?

Correct Answer:D

Question 10

Universal Containers is expecting the amount of work to increase significantly over the next three weeks. They have decided to engage a new third-party Contract Provider to help with the additional work. How should a Consultant recommend Configuring the new Contractor?

Correct Answer:D

Question 11

Universal Containers is concerned about the decrease in Asset Uptime metrics. Which two actions should a Consultant recommend?

Correct Answer:A

Question 12

Universal Containers utilizes two contractors, Contractor 1 and Contractor 2, to perform repair work, Contractor 1 has provided service longer for Universal Containers and is considered to have more repair work expertise than Contractor 2. How should a Consultant configure this expertise for Contractor 1 versus Contractor 2?

Correct Answer:C

START FSL-201 EXAM