Question 13

what is the most common energy storage solution and what are the two types

Correct Answer:D

Question 14

How is the slab and all below grade components prepared in new construction?

Correct Answer:A

Question 15

What is the appropriate fire rating requirements for an electrical room?

Correct Answer:B

Question 16

What is the recommended level of redundancy for a critical power system in a Tier III data center?

Correct Answer:B

Question 17

Which network topology uses the least amount of cabling?

Correct Answer:D

Question 18

What is the low temperature that must be maintained in a data center according to NEB standards?

Correct Answer:C