Which two of the following are reasons for considering Agile? (Choose two.)
Correct Answer:AB
Why does Scrum prevent Product Owners from changing Product Backlog items that are being worked on during the Sprint?
Correct Answer:C
A ______ chart is a graphical representation of work left to do versus time.
Correct Answer:A
You are the Scrum Master and your Development Team of 6 members has completed six Sprints with the following information:
Sprint 1: 10 pontos
Sprint 2: 11 pontos
Sprint 3: 15 pontos
Sprint 4: 14 pontos
Sprint 5: 15 pontos
Sprint 6: 10 pontos
The remaining story points for product development total 42. What is the approximate number of Sprint required to complete product development?
Correct Answer:B
Which of the following is not reflected in a Sprint Burn down Chart?
Correct Answer:B
What is the maximum amount of time that the team should spend in the daily scrum?
Correct Answer:D