- (Exam Topic 2)
Which document in the project management plan can be updated in the Plan Procurement Management process?
Correct Answer:C
- (Exam Topic 1)
Which process determines the risks that may affect the project and documents their characteristics?
Correct Answer:D
- (Exam Topic 1)
Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?
Correct Answer:B
- (Exam Topic 5)
Which of the following is a tool or technique used in the Determine Budget process?
Correct Answer:D
- (Exam Topic 6)
How can a project manager evaluate project team development?
Correct Answer:A
- (Exam Topic 5)
Which of the following is a strategy to deal with positive risks or opportunities?
Correct Answer:C