Question 145

- (Exam Topic 4)
Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?

Correct Answer:B

Question 146

- (Exam Topic 1)
Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?

Correct Answer:C

Question 147

- (Exam Topic 2)
A tool and technique used in the Develop Project Charter process is:

Correct Answer:B

Question 148

- (Exam Topic 3)
Which process involves documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans?

Correct Answer:D

Question 149

- (Exam Topic 5)
Which of the following is an estimating technique that uses the values of parameters from previous similar
projects for estimating the same parameter or measure for a current project?

Correct Answer:D

Question 150

- (Exam Topic 2)
The following is a network diagram for a project.
CAPM dumps exhibit
What is the critical path for the project?

Correct Answer:C

START CAPM EXAM