- (Exam Topic 3)
Cost baseline is an output of which of the following processes?
Correct Answer:B
- (Exam Topic 4)
A required input for Create WBS is a project:
Correct Answer:D
- (Exam Topic 2)
Which Project Time Management process includes bottom-up estimating as a tool or technique?
Correct Answer:A
- (Exam Topic 4)
Which written document helps monitor who is responsible for resolving specific problems and concerns by a target date?
Correct Answer:C
- (Exam Topic 3)
Which process is included in the Project Integration Management Knowledge Area?
Correct Answer:D
- (Exam Topic 6)
A new project has been set. Four main stakeholders besides the project manager and four other team members have been identified. How many communication channels are available?
Correct Answer:C