Question 109

- (Exam Topic 1)
Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?

Correct Answer:D

Question 110

- (Exam Topic 6)
Which of the following best correspond to the organizational process assets (OPAs) that affect the project?

Correct Answer:A

Question 111

- (Exam Topic 3)
The stakeholder register is an output of:

Correct Answer:A

Question 112

- (Exam Topic 1)
Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?

Correct Answer:B

Question 113

- (Exam Topic 4)
Types of internal failure costs include:

Correct Answer:D

Question 114

- (Exam Topic 2)
Stakeholder communication requirements should be included as a component of:

Correct Answer:C

START CAPM EXAM