- (Exam Topic 3)
Which defines the portion of work included in a contract for items being purchased or acquired?
Correct Answer:D
- (Exam Topic 3)
Conflict should be best addressed in which manner?
Correct Answer:A
- (Exam Topic 4)
Which of the following project documents is an input to the Control Scope process?
Correct Answer:C
- (Exam Topic 4)
Which of the following statements is true regarding project and product lifecycles?
Correct Answer:A
- (Exam Topic 4)
A project has an EV of 100 workdays, an AC of 120 workdays, and a PV of 80 workdays. What should be the concern?
Correct Answer:B
- (Exam Topic 4)
Which process determines the risks that might affect the project?
Correct Answer:B